New Substation Location is: 2650 S US 87
3-23-22 Land donated for the new substation,Thank you Lord!
6-14-22 Driveway off of 87 South almost complete.
7-14-22 Pad work has started!
8-18-22 Rebar and plumbing in place.
8-20-22 Blessed with base material for the substation!
8-24-22 Poured main slab with great weather.
9-07-22 Poured approach and almost framed up!
9-14-22 Tin is on. Drone Shots added, thanks Joey!
10-11-22 Rain water storage completed, let it rain!
10-20-22 Insulated and painted.
12-06-22 Nearing completion!
12-07-22 Not open yet, but the lights are on.
12-22-22 Open For Calls!
03-27-2023 Septic system completed, thank you Sefcik Construction for you generous donation!
04-26-2023 Station sign installed, Thank you FASTSIGNS!